Guide
How Subcontracting Works on Motorway Projects
Türkiyes major motorways run on the simultaneous output of dozens of subcontractors. Sections, chainage ranges, progress payments and acceptance — from the inside.
2 min read
A motorway is never one company''s job. The main contractor divides the alignment into sections, and dozens of subcontractors produce simultaneously within each. We come from inside that system: on the İzmir-İstanbul Motorway we worked in the sections of four different main contractors.
Chainage: the address of the work
On a motorway, work is defined by kilometre, not by town. The contract says "drop-channel and apron works between KM 163+300 and 224+300" — meaning that 61-kilometre strip is yours.
Real examples from our own contracts:
| Main contractor | Range | Scope |
|---|---|---|
| Göçay İnşaat | KM 125+800 – 139+400 | Drainage, stone works, earthworks, topsoil spreading |
| Astaldi | KM 163+300 – 224+300 | Drop channels and aprons |
| Nurol İnşaat | KM 224+300 – 296+500 | Surface/subsurface drainage, box culverts, 5x5 large culverts |
| Özaltın İnşaat | KM 363+450 – 408+651 | Drainage, landscaping, topsoil works |
Four contracts, roughly 193 kilometres of production. Delivering the same trade to different main contractors is a reference few firms carry: each has its own specification, its own supervision team and its own payment regime.
How the work is won
- Invitation or bid: main contractors request offers from their subcontractor pools; entry to the pool is earned with completed work and references.
- Unit-price agreement: lump sums are rare — the basis is unit price: per metre of drain, per m³ of excavation, per culvert.
- Contract and bond: the performance bond typically runs around 6% of contract value, released at acceptance.
- Site handover: your chainage is handed over by protocol; from then on, that strip''s output is your responsibility.
Three rules of the relationship
1. The supervision team has the last word
Every item is inspected before it proceeds: rebar checked before concrete, ground approved before fill. Unapproved work is demolished work — at your cost.
2. Measurement records are everything
Every item''s dimensions, sketches and photographs live in the measurement file; progress payments are approved against it. A subcontractor with weak records struggles to be paid for work actually done.
3. Programme discipline
Sections interlock: if your drainage is late, the pavement crews cannot start. Falling behind brings penalty clauses — and no invitation to the next tender.
Frequently asked
Does the subcontractor deal with the client authority?
The contract is with the main contractor; but the authority''s supervision inspects your work on site and effectively sets the quality bar.
Whose machines?
Usually the subcontractor''s own — our preference too: our fleet works on our contracts and is rented out when idle.
What are the payment terms?
Under monthly progress payments, cash typically arrives 30-60 days after approval. A firm that cannot self-finance two to three months of output should not take a large section.
Does this model travel abroad?
Yes — the section-and-measurement system is near-universal. We''ve applied it in Azerbaijan and are preparing for Libya: mobilisation lessons.
Written by: Matyol İnşaat teknik ekibi · Technically reviewed by: Yılmaz MATUR
This article is for general guidance. Binding figures and terms are those in the written quote.
Related articles
Case study
Running a Site Abroad: Mobilisation Lessons from Azerbaijan
Our first international job was motorway infrastructure and trench work. From shipping machines to keeping crews — the real cost l…
Checklist
Turkish Contractor Prequalification: What to Ask For
Before awarding work to a Turkish contractor, there are seven documents worth requesting and three claims worth verifying independ…
Glossary
Excavation Classes: From Soft Soil to Hard Rock
The same volume of excavation is priced several times higher depending on its class. Seven classes, what each looks like on site,…